New pictures are up! Click on the picture below to access the album.

The drywall was ready for primer today and a nice crew of folks got it all done before noon. We also put primer over the specialty paints in the bathrooms, so that they can receive paint again.

 

On Monday the drywall contractor is planning to texture the new drywall.

 

Monday evening we could use a crew to clean up the dust from their work. The wood trim and doors upstairs and handrails are covered with dust and need wiped down since that should be the end of the heavy dust. We can also clean up the flooring downstairs.

 

On Tuesday we should be able to primer over the texturing. Then on Wednesday we could begin painting all of the downstairs walls. If you come to paint, please bring your paint trays and roller frames and we will provide the roller covers and paint.

 

The lot was “swept” professionally today, so if you saw the dust plume on the south end of town that was us. 🙂 The lot is as clean as it has been in three weeks, though still dusty.

 

About half of the landscape islands have been cleared of muck and rocks. We would welcome any strong backs willing to tackle more of those. 🙂

 

On Friday, Pastor Rice and Bill Hendershot battled the snow and wind and stubborn muck and blew out the sprinkler system. Thanks, men!